Upcoming nightly full closures of southbound I-880

March 14, 2019

Two maps showing the effected lanes and what detours you should take

The Metropolitan Transportation Commission will conduct nightly full closures of I-880 in the southbound direction at West A Street and between Winton Avenue and State Route 92 from Sunday, March 17, through Thursday, March 21, and Sunday, March 24, through Wednesday, March 27.

Northbound 1-880 lanes 1 and 2 (the two lanes closest to the median) also will be closed for night-time construction from just south of State Route 92 to just north of West A Street.

The full southbound closure schedule is as follows:

  • 11:59 p.m. Sunday, March 17, until 4 a.m. Monday, March 18
  • 11:59 p.m. Monday, March 18, until 4 a.m. Tuesday, March 19
  • 11:59 p.m. Tuesday, March 19, until 4 a.m. Wednesday, March 20
  • 11:59 p.m. Wednesday, March 20, until 4 a.m. Thursday, March 21
  • 11:59 p.m. Sunday, March 24, until 4 a.m. Monday, March 25
  • 11:59 p.m. Monday, March 25, until 4 a.m. Tuesday, March 26
  • 11:59 p.m. Tuesday, March 26, until 4 a.m. Wednesday, March 27.
The partial northbound closure schedule is as follows:
  • 11:59 p.m. Sunday, March 17, until 5 a.m. Monday, March 18
  • 11:59 p.m. Monday, March 18, until 5 a.m. Tuesday, March 19
  • 11:59 p.m. Tuesday, March 19, until 5 a.m. Wednesday, March 20
  • 11:59 p.m. Wednesday, March 20, until 5 a.m. Thursday, March 21
  • 9 p.m. Sunday, March 24, until 5 a.m. Monday, March 25
  • 9 p.m. Monday, March 25, until 5 a.m. Tuesday, March 26
  • 9 p.m. Tuesday, March 26, until 5 a.m. Wednesday, March 27.

The closures are needed because MTC is working to convert to Express Lanes the existing I-880 HOV lanes that run southbound from Hegenberger Road to Dixon Landing Road and northbound from Dixon Landing Road to Lewelling Boulevard.  The conversion involves lane striping and the installation of signs and sign gantries, FastTrak toll tag readers, traffic monitoring video cameras and CHP observation areas. The project will result in 51 Express Lane miles from Oakland to Milpitas.  It is slated for completion by early 2020.

For maps of these upcoming I-880 closures and planned detour routes, see the MTC Bay Area Express Lanes Traffic Advisory on the City of Hayward website.