La Vista Park

South Hayward is getting a new 39-acre hillside park.

drawing of an open park at sunset overlooking Hayward

The new La Vista Park will take shape north of the extension of Tennyson Road east of Mission Boulevard and is planned as an active and passive recreation destination for the entire city—with 180-degree-plus San Francisco Bay views from a ridge trail, sports fields and courts, an amphitheater, yoga lawn and much more

The park project will remake and reclaim for public use the old La Vista Quarry.  It was originally planned as part of a 179-home subdivision next to the quarry by the quarry owner, DeSilva Gates, of Dublin.  As part the 2005 city approval of the development, DeSilva Gates is required to contribute up to $2.14 million to the now estimated $23.5 million cost of La Vista Park—but only incrementally as each new home is sold.

The recreation district is committing voter-approved Measure F1 bond proceeds and the city is pledging park “in lieu” fees on several future real estate development projects.

La Vista Park is located north of Tennyson Road and east of Mission Boulevard. The park will feature:

  • 180-degree-plus San Francisco Bay views
  • hiking trails
  • sports fields and courts
  • an amphitheater
  • yoga lawn
  • and more

The City of Hayward will oversee the building of the park with the Hayward Area Recreation and Park District (HARD).

Check out the park’s approved design (subject to change; refer to the Project Documents for detailed updates):

Concept Photos

Project Timeline

  • Update existing CEQA and present to City Council – Completed
  • Complete Construction Documents – Spring of 2024
  • Start Construction – Summer of 2024
  • Complete Construction – Estimated 12 months to 18 months

Project Documents

May 26, 2021 Special Council Infrastructure Committee Meeting

Jul. 22, 2020 Council Infrastructure Committee Meeting

Mar. 26, 2019 City Council Meeting

Award of Professional Services Agreement to SurfaceDesign, Inc., (SDI); Award of Professional Services Agreement to Langan; Appropriation of Funds; and Amendment of Resolution 18-081

Nov. 13, 2019 City Council Meeting

Informational Report regarding The DeSilva Group Conducting Partial Grading at the Future La Vista Park Site

May 15, 2018 City Council Meeting

Project Status & Funding Direction

Jan. 30, 2018 City Council Meeting

Joint Work Session with Hayward City Council and Hayward Area Recreation and Park District Board of Directors: La Vista Park Final Presentation from Surface Design Inc. and Funding Discussion

Oct. 30, 2017 City Council Meeting

Joint Meeting to Receive Updates on La Vista Park and Other Projects